Trenching completed on 2/3 of TAP route in Greece, Albania

7 December 2017 12:31 (UTC+04:00)
Trenching completed on 2/3 of TAP route in Greece, Albania

By Trend

Trenching has been completed on nearly 2/3 of the Trans Adriatic Pipeline (TAP) route in Greece and Albania, reads a message from TAP AG consortium.

This accounts for around 507km out of 765km TAP route in the mentioned countries.

“The pipeline will be buried at least 1m under the ground and will therefore be invisible,” said the message.

TAP is a part of the Southern Gas Corridor, which is one of the priority energy projects for the European Union. The project envisages transportation of gas from Azerbaijan's Shah Deniz Stage 2 to the EU countries.

The pipeline will connect to the Trans Anatolian Natural Gas Pipeline (TANAP) on the Turkish-Greek border, run through Greece, Albania and the Adriatic Sea, before coming ashore in Italy’s south.

TAP will be 878 kilometers in length (Greece 550 kilometers, Albania 215 kilometers, Adriatic Sea 105 kilometers, and Italy 8 kilometers).

TAP’s shareholding is comprised of BP (20 percent), SOCAR (20 percent), Snam S.p.A. (20 percent), Fluxys (19 percent), Enagás (16 percent) and Axpo (5 percent).

---

Follow us on Twitter @AzerNewsAz

Here we are to serve you with news right now. It does not cost much, but worth your attention.

Choose to support open, independent, quality journalism and subscribe on a monthly basis.

By subscribing to our online newspaper, you can have full digital access to all news, analysis, and much more.

Subscribe

You can also follow AzerNEWS on Twitter @AzerNewsAz or Facebook @AzerNewsNewspaper

Thank you!

Loading...
Latest See more